The purpose of this site is for information and a record of Gerry McCann's Blogs Archive. As most people will appreciate GM. deleted all past blogs from the official website. Hopefully this Archive will be helpful to anyone that is interested in Justice for Madeleine Beth McCann. Many Thanks Pamalam

 CARLOS MANUEL FIGUEIREDO PEREIRA

  

Note: This site does not belong to the McCanns it belongs to Pamalam, if you wish to contact the McCanns direct, please do not use the contact/email details on the left, use campaign@findmadeleine.com  Site Policy

P.J.TRANSLATIONS INDEX

TRANSLATIONS BY INES

CONSTRUCTION WORKER 31 MAY 07

1652 to 1653—Witness Statement of Carlos Manuel Figueiredo Pereira
06 Processos Vol VI Pages 1652 – 1653
06_VOLUME_VIa_Page_1652
06_VOLUME_VIa_Page_1653

Witness Statement
Carlos Manuel Figueiredo Pereira

Date: 2007/05/31

Occupation: Civil Engineer

He comes to the process as a witness, he works for the municipal chamber of Lagos since 1988 as a civil engineer.

With specific reference to the Urban and Environmental re-qualification works carried out in the town of Luz, namely in Rua Direita, the witness clarifies the following:

During 2006 a public tender was issued with the aim of adjudicating the firm offering the best conditions and guarantees.

This tender was won by the company Canana & Filhos Ltda and the date for starting work was established as April of the current year (2007).

During the first days/weeks of April in Rua Direita together with Largo da Republica, the different necessary infrastructures were created such as : networks for domestic drains, water supply, public lighting and telephones. These actions took place over the course of about 30 days, following others that had been implemented along Rua Helena Nascimiento Baptista.

With regard to the month of May, and after the first days of the month, work was begun at Rua Direita, aiming at the installation of water pipes, telephones and public lighting. The technical space excavated which guaranteed the application of three types of infrastructure previously mentioned, had the following average dimensions : 1,20 metres deep by 0,90 metres long, it being certain during the excavation work that they were almost immediately covered with sand and earth.


When asked how the daily checking was done, with regard to security measures and the quality of the work carried out, the witness said there was nothing abnormal to point out, it was a work that had been carried out calmly and without any incidents.

No more is said. Reads, ratifies, signs.
 